Our reviews are based upon the requirements in the TCEQ’s
“Rules and Regulations for Public Water Systems,” 30
TAC Chapter 290.38 through 290.47. You can
view these rules online, or, if you prefer,
a copy
of Chapter 290 can be downloaded. You can also download any of
our
checklists
and forms.
Submittals of Plans and
Specifications for Water System
Please submit ONLY ONE of each of the following
for plan review and approval:
- Cover letter with engineering report
- Submittal form
- TCEQ Core Data Form (for new systems)
- Click
here for Form and Instructions
- Sealed engineering plans and specifications
- Well completion data
PLEASE MAIL to:
Utilities Technical Review Team
Water Supply Division MC -153
TCEQ
P.O. Box 13087
Austin, Texas 78711-3087
|
When Is a TCEQ
Review NOT Required?
Please note that for certain distribution systems, our rules do
NOT require the submittal of engineering plans and specifications.
Review and approval MAY be required for those projects that are
defined by Section 290.39(j)(1)(D) as a significant change in an
existing distribution system that would add more than 10% of
the existing connections or 250 connections whichever is smaller.
The TCEQ must be notified of the proposed project by a Texas
professional engineer only if the distribution expansion is defined
as significant. Upon request by the TCEQ, public water systems
shall submit plans and specifications for the proposed changes.
If distribution system modifications are not defined as
significant, TCEQ review is not required. If a TCEQ response
letter is needed, a written request must be submitted to the TCEQ
for those distribution projects that are defined as not
significant.
Please be advised that even though the TCEQ will not review
engineering materials for distribution projects that are not
significant, requirements found in 30 TAC Chapter 290 must
still be met in the design and installation of the waterline
project.
TCEQ Suggested
Construction Notes That Will Help Expedite Plan Review Process
Status of Plan Reviews in
Progress
The
table of plan reviews in progress (PDF file. Help with PDF.) lists all plans that have
either: (1) not been picked up for review, or (2) are currently
under review. They are listed alphabetically by the name of the
water system. If you have any questions, e-mail us at utildist@tceq.state.tx.us
and refer to your project's log number.
Radionuclide
Testing Required for Well Completion
Several areas of Texas have groundwater with elevated
radionuclide levels. If you are drilling a well in a
county where radionuclide testing is required, you must conduct
radionuclide testing for interim approval.
For guidance on conducting this testing properly, see
How to Conduct Radionuclide Testing for Well Completion Interim
Approval.
Contact us if you have any questions.